🏗️ Safety Management Plan Builder
The seven statutory items are laid out as sections, and missing ones are flagged as you build.
| Project | Site address | ||
|---|---|---|---|
| Client / permitting body | Contractor | ||
| Start date | Completion date | ||
| Contract amount | Scale |
| Role | Name | Qualification | Duties | Contact |
|---|---|---|---|---|
| Stage | Timing | Items | Monitoring / CCTV | Inspector |
|---|---|---|---|---|
Adjacent structures: Blasting, vibration and noise: Groundwater and settlement: Early-warning instrumentation: Work stops immediately on any warning sign and is reported to the client.
Traffic safety facilities: Pedestrian route: Site vehicle access: Flaggers: Sections affecting traffic are coordinated with the police and road authority in advance.
| Item | Planned | Timing | Note |
|---|---|---|---|
Periodic training: Training on hire and on any change of task Emergency contacts: On an accident: stop work, treat the injured, call 119, report to the client, preserve the scene Nearest hospital:
| Work type | Method / sequence | Key hazards | Controls | Period |
|---|---|---|---|---|
Review and submission The plan is submitted to the client or the permitting body. For Class 1 and 2 facility works under Article 7(1)-(2) of the Special Act on the Safety Control of Public Structures, review is carried out by the Korea Authority of Land and Infrastructure Safety; for other works, by a safety inspection agency designated by the client or permitting body. The reviewing body must notify the result within 20 days of receipt, classified as adequate, conditionally adequate, or inadequate. An inadequate result requires the plan to be revised and resubmitted. For Class 1 and 2 facility works, the approved plan is registered on the Construction Safety Management Integrated Information System (CSI, www.csi.go.kr).
| Submitted on | Prepared by | Reviewed by | Submitted by |
|---|---|---|---|
| Date: (Sign) | Date: (Sign) | Date: (Sign) | Date: (Sign) |
Paste into ChatGPT or Claude to tailor it to your situation
🖨️ Choose "Save as PDF" in the print dialog to get a PDF file
📄 Opens and edits directly in Word or Hangul (.doc)
💡 State the statutory triggerRecommended
Naming which sub-paragraph applies (10m excavation, 10+ floors, tower crane) makes the reviewer's job easier.
📖 건설기술 진흥법 시행령 제98조 제1항
You may omit these. We only tell you the risk.
- TitleSafety plan (statutory) · 12/12
- Project overviewProject overview (full) · 12/12
- Safety organisationSafety organisation (roster) · 12/12
- Inspection planInspection plan by stage (table) · 12/12
- Surrounding areaSurrounding area controls (narrative) · 12/12
- Traffic safetyTraffic safety plan · 12/12
- Safety budgetSafety budget plan (table) · 12/12
- Training and emergencyTraining and emergency plan · 12/12
- Plan by work typePlan by work type (table) · 12/12
- Review procedureReview procedure · 12/12
- Review and submissionReview and submission · 12/12
- LogoCompany logo · 3/12
Drag or use the arrows. ⇥ places a block beside the row above, ⇤ gives it its own row again. +− adjust one column; side-by-side items trade width with each other.
Colors stay; only the header, tables and signature layout change
Harbor Mist
Tap a swatch to lock that color
Tone
- Logo
- Title
- Project overview
- Safety organisation
- Inspection plan
- Surrounding area
- Traffic safety
- Safety budget
- Training and emergency
- Plan by work type
- Review procedure
- Review and submission
What you type stays in this browser. Nothing is sent to a server.
⚠️ The plan must be submitted to the client or permitting body before commencement, after review by the supervisor or construction manager (Enforcement Decree Art. 98(2)). This tool builds the outline only; detailed plans by work type and structural reviews must be prepared separately. Not legal advice.
We build ISO documentation systems and Daou Office approval forms to order
ISO documents structured the way audits expect, and groupware approval forms shaped around how your company actually works.
- ISO 9001, 14001 and 45001 documentation — manual, procedures, work instructions and record forms as one coherent set.
- Custom Daou Office approval forms — approval routes, required fields and acceptance criteria filled in, not empty templates.
- No off-the-shelf template pack. Each document is reworked around your industry and your processes.
We do not represent you at certification audits and do not guarantee certification. Our scope ends at building the documents and the system.
What this tool does
A safety management plan is filed with the client or permitting body before construction starts. Article 62 of the Construction Technology Promotion Act is the basis, and Article 99(1) of its Enforcement Decree fixes exactly what the plan must contain in seven items. This builder turns those seven into sections, so you can see at a glance whether one is missing. The two that most often draw requests for supplementation are the traffic safety plan and the plan by work type, because both are separate statutory items yet are frequently folded into the general overview. The plan must be submitted before commencement, and before that it must be reviewed and confirmed by the construction supervisor or construction management engineer.
Who uses this
- Preparing a first plan for a project with excavation deeper than ten metres
- Discovering late that a tower crane or pile driver brings the project within scope
- Revising a plan that came back with a conditional approval
- Filing an amended plan after a design change altered the construction method
- Checking a client's requested contents against the statutory items
How to use
- 1In the project overview, pick the block that also states the statutory trigger so the reviewer immediately sees which sub-paragraph applies.
- 2Work down the seven statutory sections. Anything left empty is listed in the requirements panel.
- 3For bulky items such as plans by work type, choose the attachment block and keep only the outline in the body.
- 4Copy the document into your word processor, or copy the AI prompt to refine the wording.
The seven statutory items
Article 99(1) of the Enforcement Decree lists what the plan must include. First, the project overview and the safety organisation. Second, the inspection plan by construction stage, which must cover the installation and operation of monitoring instruments and CCTV. Third, controls for the area around the site, including damage prevention for blasting, vibration, noise and groundwater cut-off, and instrumentation to detect warning signs during excavation. Fourth, the installation of traffic safety facilities and the traffic flow plan. Fifth, the execution plan for the safety budget. Sixth, safety training and the emergency response plan. Seventh, plans by work type, including construction methods and sequences for each facility. Omitting any one of the seven draws a request for supplementation.
Worked examples
Deep excavation
State the excavation depth in the overview and pair the surrounding-area controls with adjacent structures and the instrumentation plan. Naming how many inclinometers and piezometers are installed and how often they are read satisfies the early-warning requirement.
Urban roadside works
Do not leave the traffic section thin. Record fencing and cones, the pedestrian diversion, delivery time windows, flagger positions, and the fact that the police and road authority were consulted.
Amended submission
Switch the title to the revision variant and state what changed and why in the overview. Amendments follow the same rule: submit before commencement, after supervisor review.
Frequently asked questions
How do I know whether my project needs a plan?
Article 98(1) of the Enforcement Decree lists the triggers: works on class 1 and class 2 facilities, excavation of ten metres or more, use of explosives where a structure lies within twenty metres or livestock within one hundred metres, buildings of ten to under sixteen storeys, remodelling or demolition of buildings of ten storeys or more and vertical-extension remodelling, and use of registered plant such as boring rigs ten metres or taller, pile drivers and extractors, and tower cranes. Projects the client or permitting body deems to need particular safety management are also covered. Nuclear facility works are excluded.
When must it be submitted?
Before commencement. Article 98(2) requires submission to the client or permitting body before the works start, and requires prior review and confirmation by the construction supervisor or construction management engineer. The same applies when the plan is amended. A submission date later than the start date is itself a problem, so check the dates.
How long does review take?
The client or permitting body must notify the result within twenty days of receiving the plan. The verdict is one of three: appropriate, conditionally appropriate, or inappropriate. A conditional verdict means the gaps are not critical to safety but some supplementation is needed, and the reasons come with the approval letter. An inappropriate verdict requires the plan to be changed.
Can it be merged with the hazard prevention plan?
Yes. Where the project also requires a hazard prevention plan under Article 42 of the Occupational Safety and Health Act, the second sentence of Article 98(1) allows the two plans to be prepared together. Even when merged, every item required by each statute must still appear, so check the combined contents against both lists.
Is stating the budget amount enough?
No. The article calls for an execution plan, not just a figure. Record what will be spent on each item, when, and who is responsible. The table block in this builder splits item, amount and timing into separate columns so the timing is hard to skip.
Can I submit the output as it is?
Treat it as a skeleton. This builder produces the outline and narrative frame for the seven statutory items. A real submission also carries attachments such as detailed plans by work type, retaining-wall structural reviews, instrumentation layouts and temporary-structure calculations. Article 99(2) leaves the detailed standards to ministerial rules, so follow any specific format your client requires.
Cautions
- •Submit before commencement. A submission date later than the start date is a procedural breach in itself.
- •Prior review by the supervisor or construction management engineer is required; skipping it gets the plan returned at intake.
- •This builder produces the outline only. Structural reviews and instrumentation layouts must be prepared separately.
- •Statutes change. Confirm the current text of Articles 98 and 99 before submitting.